Road Closure Update for Junction Work

24/07/2025

Good morning,

To facilitate the safe construction of junctions connecting the newly established temporary road with the existing carriageway, two road closures were originally scheduled—one of which was set for this weekend.

We are now pleased to inform you that the closure scheduled for this weekend is no longer required.

However, please be aware the evening closures on Friday, 1st August and Saturday, 2nd August will proceed as planned.

As advised previously the road will be closed from 19:00 to 07:00 on both Friday and Saturday nights. Outside of these hours, the road will remain open to traffic.

When the road is closed a fully signed diversion will be in place via the A5092, A590, and A595, passing through Greenodd, Ulverston, and Askam in Furness. Please note that access for emergency service vehicles will be maintained throughout the duration of the works.

We a